Pri Mlynoch has commenced construction work.
-
3. 10. 20253. 10. 2025
The construction of the project started with the excavation and stabilization of the construction pit in the 41st week, based on a valid building permit for these parts of the project.
The execution of the construction pit and special foundation works is expected to take 5-6 months, with the foundational slab and superstructure planned to follow in February/March 2026.
Currently, a selection process is underway to choose the main contractor for the construction.
You can read more in the article: https://www.yimba.sk/pri-mlynoch/bratislava-dostane-novu-vezu-iuris-startuje-vystavbu-projektu-pri-mlynoch-prace-zacinaju-o-par-dni